Happy 4th of July!!  I hope everyone had a safe and fun-filled holiday.  With the summer being in full swing, we are also at full speed with all our projects on campus.  This summer seems to have an even busier schedule than we have in the past.

Here is a summary of some of the projects that have been started at St. Joseph’s Indian School:

Drainage Project:

This week the company we’re working with pulled onto campus with their big equipment and began removing the concrete in front of the Benedictine and Kateri Buildings. First, second and third grade students have their homes in the Benedictine Building, while the Kateri Building houses high school girls.

Mathias Remodel:

We are finishing up with the Mathias Remodel.  Right now the guys are working on their punch list to get the final details finished up just in time for the houseparents to arrive on campus in the next couple of weeks. The junior high girls who live in the Mathias Home will return to campus on August 12 for school to begin Monday morning, August 13.

School Painting and Carpeting:

St. Joseph’s Elementary School is getting a little touch up this summer also.  We are re-painting all the classrooms and laying new carpet.

Summerlee and William Remodel:

We have kicked off the next round of home remodels with the Summerlee and William Homes, where our fourth and fifth-grade girls live.  The Summerlee Home has most of the demolition work complete. We have started framing up the new walls, which will reposition some of the rooms to give the houseparents a better view of kids during activities taking place in the home.

The William Home is in the demolition process.  This home will be extended a few feet to give the girls who live there more room in their living and play spaces.

The projects listed above are some of the bigger projects we have going on around campus.  We also have the Akta Lakota Museum & Cultural Center expansion, which will add an alumni center, historical center and storage for the museum’s collection of art and artifacts.

Some of our daily work activities going on around campus include:

Grounds:

  • Irrigation and mowing at Fisher Field, where our junior high students spend time playing after school and on weekends.

Plumbing:

  • Plumbing in the Summerlee Home is roughed in and the Mathias Home plumbing completed.  The plumbing that has been inspected has passed both inspections.

Painting:

  • Crew member Jeff is painting the Giles Home and should be finished this week.

Electrical:

  • Finish wiring the Mathias Home, demo of electrical in Summerlee. Wiring new equipment at Tipi Press Printing and Development rooftop AC unit.

Mechanics:

  • Annual vehicle inspections and daily maintenance.  St. Joseph’s fleet has 22 vehicles that insurance company totaled due to a recent hail storm.

Author: St. Joseph's Indian School

At St. Joseph's Indian School, our privately-funded programs for Lakota (Sioux) children in need have evolved over 90 years of family partnership, experience and education. Because of generous friends who share tax-deductible donations, Native American youth receive a safe, stable home life; individual counseling and guidance; carefully planned curriculum based on Lakota culture and individual student needs and tools to help build confidence, boost self-esteem and improve cultural awareness. All of this helps children to live a bright, productive, possibility-filled future.

0 thoughts on “Guest Blogger: Facilities Team”

Leave a Reply

Your email address will not be published. Required fields are marked *